Kalanagar.

Ward H/E · Kalanagar · redevelopment · stage under-construction · sanctioned FSI 3.0

Regulation changes that reach this project

SeverityCircularWhat it means here
review IGR/RR/2026/ANN-II
2026-10-16
Annual statement of rates revision for Mumbai city and suburban districts
charge change, because this project's locality is one of Malabar Hill, Santa Cruz or Kalanagar
informational CHE/PROC/2026/0092
2026-10-17
Online submission of amended plans: mandatory annexure format
General circular, no project-specific conditions stated.

Design changes in flight

DC-116 · Podium parking layout revised, two bays removed
design Laxmi Arya · by 2026-10-19 · with them now
costing Costing lead · by 2026-10-22 · waiting
approvals Vikram · by 2026-10-26 · waiting
construction Construction lead · by 2026-10-28 · waiting